What happens if a server has multiple schedules that overlap?

As a schdule becomes more specific, CMM gives higher priority to it. So a schedule that applies to a specific date would be higher priority than a schedule that applies to a particular day of the week, which in turn is higher priority than a schedule that applies to every day.


For example, a serer has two schedules applied to it - one is a schedule to be on demand on every weekday and the other is to be turned off on December 25th. Because the December 25th schedule is more specific, it will take priority over the every weekday schedule if they clash. In other words, the server will be turned off on December 25th, even if it is on a weekday.